Dynamic Instruments – Kusile Power Station
What a positive start to the new year. We started this year with a splicing project.
This project required us to splice and test more than 700 splices at Kusile power station.
The splicing and testing was done at 6 different sub stations at Kusile
The Kusile power station project, which is located near the existing Kendal power station, in the Nkangala district of Mpumalanga, will comprise six units, each rated at an 800 MW installed capacity for a total capacity of 4 800 MW. Once completed, Kusile will be the fourth-largest coal-fired power station in the world.
Eskom – Matimba Power Station
Fibre installation, For this project we at OFT were required to install 750m Optic Fibre cable ,splice and test the cable.
The cable was successfully installed, spliced and tested.
All testing of cable is done with an optical time-domain reflectometer (OTDR).
An optical time-domain reflectometer (OTDR) is an optoelectronic instrument used to characterize an optical fibre. An OTDR is the optical equivalent of an electronic time domain reflectometer.
Upcoming Projects
Yards – Arial Installations
61Km of Arial cable will be installed over 12 different yards all over Gauteng , Kwazulu Natal , North west ,Limpopo and Mpumalanga
Korenix switches and converters will also be installed at these sites.
OFT will be responsible for cable installation , splicing ,testing and installation of all converters and switches.